Larsen & Toubro Limited, Construction
Date : 21/1/2017
Description : Fabrication and erection of more than 7.0 lakhs inch meter piping work comprising of pipe size ranging from 15mm to 1000mm & 1020-ton pipe supporting, conveyors & equipment & building structures / pipe racks and erection of 1572-ton of pump house equipment including its auxiliary group of 7 pumps houses and rotary equipment external water system for SMS III project (pkg. No. 077-01a)
Quantity : Lot
Status : Completed